edited by
770 views
3 votes
3 votes

Ramesh and Ganesh can together complete a work in $16$ days. After seven days of working together, Ramesh got sick and his efficiency fell by $30\%$. As a result, they completed the work in $17$ days instead of $16$ days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?

  1. $13.5$
  2. $11$
  3. $12$
  4. $14.5$
edited by

1 Answer

1 votes
1 votes

Let, the efficiency of Ramesh is $\text{‘R’} \; \text{unit/day}. $

And, the efficiency  of Ganesh is $\text{‘G’} \; \text{unit/day}.$

We know that, $ \boxed{\text{Total work done = Total time} \times  \text{Efficiency}} $

Now, Total work $ = 16 (\text{R + G}) \; \text{units} $

Work done in $ 7 \; \text{days},$ when they working together $ = 7 (\text{R+G}) \; \text{units} $

Remaining work $ = 16 \left(\text{R+G}) – 7( \text{R+G}\right) = 9\left( \text{R+G}\right) \; \text{units} $

Ramesh got sick and his efficiency fell by $30 \%.$ That means he will work $70\% \left( \frac{70}{100} = \frac{7}{10} \right)$ of his efficiency.

Now, they worked together and complete the work in $17 \; \text{days}.$

Remaining days they worked $ = 17 – 7 = 10 \; \text{days}.$

So, $ 10 \times \left( \frac{7}{10}\text{R + G} \right) = 9 ( \text{R+G}) $

$ \Rightarrow 10 \times \left( \frac{\text{7R+10G}} {10} \right) = \text{9R+9G} $

$ \Rightarrow \text{G} = \text{2R} $

$ \Rightarrow \boxed{\text{R} = \frac{\text{G}}{2}} $

If Ganesh had worked alone after Ramesh got sick. Then,

  • Remaining work $ = 9( \text{R+G}) \; \text{units}$
  • Efficiency $ = \text{G} \; \text{unit/day} $

So, $ 9( \text{R+G}) = \text{Time} \times \text{G} $

$ \Rightarrow 9 \left( \frac{\text{G}}{2} + \text{G}\right) = \text{Time} \times \text{G} $

$ \Rightarrow 9 \times \frac{3\text{G}}{2} = \text{Time} \times \text{G} $

$ \Rightarrow \text{Time} = \frac{27}{2} $

$ \Rightarrow \boxed{ \text{Time} = 13 . 5 \; \text{days}} $

$\therefore$ The Ganesh had worked alone after Ramesh got sick. Then time taken by him to complete the remaining work is $ 13.5 \; \text{days}.$

Correct Answer $: \text{A}$

edited by
Answer:

Related questions

3 votes
3 votes
1 answer
3
go_editor asked Mar 20, 2020
653 views
The value of the sum $7 \times 11 + 11 \times 15 + 15 \times 19 + \dots$ + $95 \times 99$ is$80707$$80773$$80730$$80751$
3 votes
3 votes
1 answer
4
go_editor asked Mar 20, 2020
700 views
How many two-digit numbers, with a non-zero digit in the units place, are there which are more than thrice the number formed by interchanging the positions of its digits?...
2 votes
2 votes
1 answer
5
go_editor asked Mar 20, 2020
785 views
The smallest integer $n$ such that $n^{3} - 11n^{2} + 32n - 28 >0$ is