3 3 votes Machine M1 as well as Machine M2 can independently produce either Product P or Product Q. The times taken by machines M1 and M2 (in minutes) to produce one unit of product P and Q are given in the table below: (Each machine works 8 hours per day). PRODUCT M1 M2 P 10 8 Q 6 6 What is the least number of machine hours required to produce 30 pieces of P and 25 pieces of Q? 6 hours 30 minutes 7 hours 24 minutes 5 hours 48 minutes 4 hours 6 minutes Quantitative Aptitude cat1995 quantitative-aptitude work-time + – Misbah Ghaya 8.6k points 4.8k views answer comment Share Follow Print 0 reply Please log in or register to add a comment.
1 1 vote As the answer requires least number of machine hours required to produce 30 pieces of P and 25 pieces of Q So, we'll go by which m/c takes less time to produce product p & product Q M/C M2 consumes less time to produce product P M/C M1 & M2 both consumes same time to produce product Q Time taken by M2 to produce 30 pieces of P = 30 * 8 = 240 min Time taken by M1 or M2 to produce 25 pieces of Q = 25 * 6 = 150 min ∴ Least number of machine hours required to produce 30 pieces of P and 25 pieces of Q is (240 + 150)min = 390 min = 6hrs and 30min Sukanya Das answered Feb 28, 2018 Sukanya Das 5.5k points comment Share Follow 0 reply Please log in or register to add a comment.