0 votes 0 votes A and B took a job to be completed in 20 days. They started working together and after 12 days, C joined them and the whole job finished in 15 days. How much time would C require to complete the job if only C was hired? altamash asked Apr 16, 2019 altamash 68 points 4.6k views answer comment Share See all 0 reply Please log in or register to add a comment.
2 votes 2 votes Here A, B and C are the no. of days taken by them to complete the given job respectively. Hence, the time taken by C to complete the job is 12. Ravi R Y answered Jun 14, 2019 Ravi R Y 94 points comment Share See all 0 reply Please log in or register to add a comment.