$\text{A, B}$ and $\text{C}$ can do a piece of work in $24, 30$ and $40$ days respectively. They began the work together but $\text{C}$ left $10$ days before completion of the work. In how many days was the work done ?
- $11$ days
- $11.5$ days
- $12.5$ days
- $12$ days