0 0 votes It takes $6$ technicians a total of $10$ hours to build a new server from direct computer, with each working at the same rate. If six technicians start to build the server at $11:00$ am, and one technician per hour is added beginning at $5:00$ pm, at what time will the server be completed? $6:40$ pm $7:00$ pm $7:20$ pm $8:00$ pm Quantitative Aptitude cat2009 quantitative-aptitude work-time + – Misbah Ghaya 8.9k points 2.1k views answer comment Share Follow Print 0 reply Please log in or register to add a comment.
Best answer 1 1 vote To complete the job 6*10=60 man/hours are needed. By 5:00 PM 6*6=36 man/hour done. 24 is left. 5:00 PM - 6:00 PM 7 man/hour; ->36+7=43 6:00 PM - 7:00 PM 8 man/hour; ->43+8=51 7:00 PM - 8:00 PM 9 man/hour. ->51+9=60(work completed) Hence,Option(D)8:00 pm. Leen Sharma answered Jul 31, 2016 • selected Aug 1, 2016 by Arjun Leen Sharma 11.6k points comment Share Follow 0 reply Please log in or register to add a comment.