Q1)Srinu is 50% more efficient than Murali.If Srinu takes 20 days to finish a job then Murali will take how much time?
in Quantitative Aptitude by (794 points) 3 10 27
retagged by | 280 views

2 Answers

+2 votes
Best answer
Since Srinu is more efficient, Murali should take more days.

No. of days Murali will take $ = 20 \times 1.5 = 30$ days.
by (8k points) 52 69 114
selected by
+1
Thank you so much sir
0 votes
30