2 votes 2 votes Q1)Srinu is 50% more efficient than Murali.If Srinu takes 20 days to finish a job then Murali will take how much time? Quantitative Aptitude quantitative-aptitude work-time + – Lakshman Bhaiya asked Nov 25, 2017 • retagged Dec 12, 2017 by Arjun Lakshman Bhaiya 13.7k points 1.4k views answer comment Share See all 0 reply Please log in or register to add a comment.
Best answer 2 votes 2 votes Since Srinu is more efficient, Murali should take more days. No. of days Murali will take $ = 20 \times 1.5 = 30$ days. Arjun answered Nov 25, 2017 • selected Nov 25, 2017 by Lakshman Bhaiya Arjun 8.6k points comment Share See 1 comment See all 1 1 comment reply Lakshman Bhaiya 13.7k points commented Nov 25, 2017 reply Share Thank you so much sir 1 votes 1 votes Please log in or register to add a comment.
0 votes 0 votes 30 roshan2207 answered Nov 26, 2017 roshan2207 18 points comment Share See all 0 reply Please log in or register to add a comment.