Month Stage Cost(Rs. '000 per man-month)
$1-2$ Specification $40$
$3-4$ Design

$20$

$5-8$ Coding

$10$

$9-10$ Testing

$15$

$11-15$ Maintenance $10$

The number of people employed in each month is:

Month $1$ $2$ $3$ $4$ $5$ $6$ $7$ $8$ $9$ $10$ $11$ $12$ $13$ $14$ $15$
No. of people employed $2$ $3$ $4$ $3$ $4$ $5$ $5$ $4$ $4$ $1$ $3$ $3$ $1$ $1$ $1$

Which five consecutive months have the lowest average cost per man-month under the new technique?

  1. $1-5$ 
  2. $9-13$
  3. $11-15$ 
  4. None of the these

1 Answer

0 0 votes

Here, new technique refers to the design stage is performed in $3,4, \& \hspace{0.1cm} 5^{th} month$ & in the $5^{th}$ month $5$ people are working on the design stage. And the coding stage was finished in $6^{th} - 8^{th}$ months.

The new table will be look like:

Month Stage Cost(Rs. '000 per man-month)
$1-2$ Specification $40$
$3-5$ Design

$20$

$6-8$ Coding

$10$

$9-10$ Testing

$15$

$11-15$ Maintenance $10$

The number of people employed in each month is:

Month $1$ $2$ $3$ $4$ $5$ $6$ $7$ $8$ $9$ $10$ $11$ $12$ $13$ $14$ $15$
No. of people employed $2$ $3$ $4$ $3$ $5$ $5$ $5$ $4$ $4$ $1$ $3$ $3$ $1$ $1$

$1$

We can clearly see that, the maintenance stage has the lowest average cost per man-month .

In the $1-5$ month span,

average cost per man-month in $1-2$ month is $40,000$

average cost per man-month in $3-5$ month is $20,000$

So, average cost per man-month in $1-5$ month is = $\dfrac{(40,000+20,000)}{2} = 30,000$

In the $9-13$ month span,

avg. cost per man-month in $9-10$ month is $15,000$

avg. cost per man-month is $10-13$ month is $10,000$

So, avg. cost per man-month in $9-13$ month is $\dfrac{(15,000+10,000)}{2} = 12,500$

In the $11-15$ month span, average cost per man-month is $10,000$

So, the $11-15$ month span will be having lowest average cost per man-month under the new technique.

Answer is option C)

• edited by
Position:
Show:

Related questions

2 2 votes
2 2 answers
3.0k
3.0k views
Misbah Ghaya asked Jul 20, 2017
3,041 views
The amount of money invested (in rupees crore) in the core infrastructure areas of two districts, Chittoor and Khammam, Andhra Pradesh as follows:If the total investment ...
2 2 votes
1 1 answer
2.8k
2.8k views
Misbah Ghaya asked Jul 20, 2017
2,831 views
The amount of money invested (in rupees crore) in the core infrastructure areas of two districts, Chittoor and Khammam, Andhra Pradesh as follows:In Khammam district the ...
2 2 votes
1 1 answer
2.6k
2.6k views
Misbah Ghaya asked Jul 20, 2017
2,565 views
The amount of money invested (in rupees crore) in the core infrastructure areas of two districts, Chittoor and Khammam, Andhra Pradesh as follows:Approximately how many t...
2 2 votes
2 2 answers
2.8k
2.8k views
Misbah Ghaya asked Jul 20, 2017
2,845 views
The amount of money invested (in rupees crore) in the core infrastructure areas of two districts, Chittoor and Khammam, Andhra Pradesh as follows:By what percent was the ...
1 1 vote
0 0 answers
1.2k
1.2k views
Misbah Ghaya asked Jul 20, 2017
1,209 views
MonthStageCost(Rs. '000 per man-month)$1-2$Specification$40$$3-4$Design$20$$5-8$Coding$10$$9-10$Testing$15$$11-15$Maintenance$10$The number of people employed in each mon...