Bob can finish a job in $40$ days, if he works alone. Alex is twice as fast as Bob and thrice as fast as Cole in the same job. Suppose Alex and Bob work together on the first day, Bob and Cole work together on the second day, Cole and Alex work together on the third day, and then, they continue the work by repeating this three day roster, with Alex and Bob working together on the fourth day, and so on. Then, the total number of days Alex would have worked when the job gets finished, is
edited by

Please log in or register to answer this question.

Answer:

Related questions

1 votes
1 votes
1 answer
1
1 votes
1 votes
1 answer
2
admin asked Mar 3, 2023
1,740 views
If $c=\dfrac{16 x}{y}+\dfrac{49 y}{x}$ for some non-zero real numbers $x$ and $y,$ then $c$ cannot take the value$-60$ $-50$ $60$ $-70$
2 votes
2 votes
1 answer
3
admin asked Mar 3, 2023
400 views
If $(3+2 \sqrt{2})$ is a root of the equation $a x^{2}+b x+c-0$, and $(4+2 \sqrt{3})$ is a root of the equation $a y^{2}+m y+n – 0$, where $a, b, c, m$ and $n$ are inte...
1 votes
1 votes
0 answers
4
admin asked Mar 3, 2023
315 views
Suppose the medians $\mathrm{BD}$ and $\mathrm{CE}$ of a triangle $\mathrm{ABC}$ intersect at a point $\mathrm{O}$. If area of triangle $\mathrm{ABC}$ is $108$ $\mathrm{s...