A group of $\mathrm{N}$ people worked on a project. They finished $35 \%$ of the project by working $7$ hours a day for $10$ days. Thereafter, $10$ people left the group and the remaining people finished the rest of the project in $14$ days by working $10$ hours a day. Then the value of $\mathrm{N}$ is

  1. $150$
  2. $36$
  3. $140$
  4. $23$
in Quantitative Aptitude edited by
by
3.7k points
167 views

1 Answer

0 votes
0 votes

Answer: C

 