N-Nuts B-Bolts M-Minute
100 N/M so to produce 1000 N ->>10 Min
Then 5 min for cleaning so total 10+5=15 min (for 1000 Nut production & Cleaning)
To produce 8000 N it will take 8 times 15 min =120 min
Now to produce next 1000 N it'll take only 10 min (No need to clean)
So 120+10=130 Min to produce 9000/Nuts
Now Come to Bolt(B)
75 B/M so to produce 1500B ->>(1500/75)=20 Min
Then 10 min for cleaning so total 20+10=30min (for 1500 Bolt production & Cleaning)
To produce 7500 B it will take 5 times 30 min=150min
Now to produce next 1500 B it'll take only 20 min (No need to clean)
So 150+20=170 Min to produce 9000/Bolts
Now as given in Question both production are done simultaneously So to produce 9000 Bolts and nuts it will take minimum time= max(9000 Nut production time, 9000 Bolt production time)=(130 min ,170 min)=170 min
So, Option(3) is Ans.