A and B took a job to be completed in 20 days. They started working together and after 12 days, C joined them and the whole job finished in 15 days. How much time would C require to complete the job if only C was hired?

1 Answer

2 votes
2 votes

Here A, B and C are the no. of days taken by them to complete the given job respectively.

Hence, the time taken by C to complete the job is 12.

Related questions

0 votes
0 votes
1 answer
1
altamash asked Apr 19, 2019
1,056 views
A can do a certain work in the same time in which B and C together can do it.If A and B together could do it in 10 days and C can alone in 50 days,then B alone in 50 day...
0 votes
0 votes
2 answers
2
altamash asked Apr 19, 2019
1,172 views
A can do piece of work in 4 hours: B and C together can do it in 3 hours,while A and C together can do it in 2 hours. how long will B alone take to do it?
0 votes
0 votes
1 answer
3
altamash asked Apr 17, 2019
1,926 views
3 men and 4 women can complete a work in 10 days by working 12 hours a day. 13 men and 24 women can do the same work by working same hours a day in 2 days. How much time ...
2 votes
2 votes
2 answers
4
Lakshman Bhaiya asked Nov 25, 2017
1,357 views
Q1)Srinu is 50% more efficient than Murali.If Srinu takes 20 days to finish a job then Murali will take how much time?
3 votes
3 votes
1 answer
5
suvasish pal asked Aug 27, 2017
15,984 views
$\text{A}$ alone can do a piece of work in $6$ days and $\text{B}$ alone in $8$ days. $\text{A}$ and $\text{B}$ undertook to do it for Rs. $3200.$ With the help of $\text...