A and B took a job to be completed in 20 days. They started working together and after 12 days, C joined them and the whole job finished in 15 days. How much time would C require to complete the job if only C was hired?
in Quantitative Aptitude by (56 points) 5 12 | 100 views

1 Answer

+2 votes

Here A, B and C are the no. of days taken by them to complete the given job respectively.

Hence, the time taken by C to complete the job is 12.