Month |
Stage |
Cost(Rs. '000 per man-month) |
$1-2$ |
Specification |
$40$ |
$3-4$ |
Design |
$20$
|
$5-8$ |
Coding |
$10$
|
$9-10$ |
Testing |
$15$
|
$11-15$ |
Maintenance |
$10$ |
The number of people employed in each month is:
Month |
$1$ |
$2$ |
$3$ |
$4$ |
$5$ |
$6$ |
$7$ |
$8$ |
$9$ |
$10$ |
$11$ |
$12$ |
$13$ |
$14$ |
$15$ |
No. of people employed |
$2$ |
$3$ |
$4$ |
$3$ |
$4$ |
$5$ |
$5$ |
$4$ |
$4$ |
$1$ |
$3$ |
$3$ |
$1$ |
$1$ |
$1$ |
What is the difference in the cost between the old and the new techniques?
- Rs. $30,000$
- Rs. $60,000$
- Rs. $70,000$
- Rs. $40,000$