Month Stage Cost(Rs. '000 per man-month)
$1-2$ Specification $40$
$3-4$ Design

$20$

$5-8$ Coding

$10$

$9-10$ Testing

$15$

$11-15$ Maintenance $10$

The number of people employed in each month is:

Month $1$ $2$ $3$ $4$ $5$ $6$ $7$ $8$ $9$ $10$ $11$ $12$ $13$ $14$ $15$
No. of people employed $2$ $3$ $4$ $3$ $4$ $5$ $5$ $4$ $4$ $1$ $3$ $3$ $1$ $1$ $1$

With reference to the above question, what is the cost incurred in the new “Coding” stage? (Under the new technique, $4$ people work in the sixth month and $5$ in the eighth).

  1. Rs. $1,40,000$ 
  2. Rs. $1,50,000$ 
  3. Rs. $1,60,000$ 
  4. Rs. $1,70,000$