At Weird Holiday Company, an employee gets a holiday on those days whose first letter is the same as the first letter of the employee’s name. All other days are working days. For instance, William gets a holiday on each Wednesday. Assume that the daily productivity of all employees is the same.
Raja stated the work on Sunday, the $25$th February $1996$ and finished the work on March $2$, $1996$. If Tom and Jerry were assigned this task on $25$th February $1996$, when will the work have been completed?
- $26$th February $1996$
- $1$st March $1996$
- $28$th February $1996$
- Tom and Jerry cannot possibly work together